2022 Paving and Sidewalk Repair Program
Proposed Paving List CY 2022
STREET NAME | FROM STREET | TO STREET | WARD | REPAIR METHOD | ESTIMATED START | ESTIMATED DURATION* |
MARCH STREET | BRIDGE ST | MARCH ST CT | 2 | MILL & OVERLAY | AUGUST | 3 WEEKS |
BRIDGE STREET | ARBELLA ST | BARTON ST | 2 | MILL & OVERLAY | AUGUST | 3 WEEKS |
FEDERAL STREET | SAINT PETER ST | WASHINGTON ST | 2 | MILL & OVERLAY | AUGUST | 3 WEEKS |
ST PETER STREET | FEDERAL ST | CHURCH ST | 2 | MILL & OVERLAY | AUGUST | 3 WEEKS |
MOONEY ROAD | HIGHLAND AVE | SEEMORE ST | 4 | SIDEWALK REPAIRS MILL & OVERLAY | AUGUST | 5-6 WEEKS |
SEEMORE STREET | MOONEY RD | DEAD END | 4 | SIDEWALK REPAIRS MILL & OVERLAY | AUGUST | 5-6 WEEKS |
FREEMAN ROAD | HIGHLAND AVE | DEAD END | 4 | MILL & OVERLAY | AUGUST | 3 WEEKS |
CROWDIS STREET | HIGHLAND AVE | MALM AVE | 4 | MILL & OVERLAY | AUGUST | 3 WEEKS |
GREENLAWN AVENUE | MARLBOROUGH RD | VERONA ST | 4 | MILL & OVERLAY | AUGUST | 3 WEEKS |
GREENLAWN AVENUE | VERONA ST | DEAD END | 4 | MILL & OVERLAY | AUGUST | 3 WEEKS |
SCENIC AVENUE | MARLBOROUGH RD | SCENIC TER | 4 | MILL & OVERLAY | AUGUST | 3 WEEKS |
SCENIC AVENUE | SCENIC TER | SCENIC WY | 4 | MILL & OVERLAY | AUGUST | 3 WEEKS |
BRADFORD STREET | LOVETT ST | BALCOMB ST | 6 | MILL & OVERLAY | AUGUST | 3 WEEKS |
BRADFORD STREET | LOVETT ST | LOVETT ST | 6 | MILL & OVERLAY | AUGUST | 3 WEEKS |
BRADFORD STREET | TREMONT ST | LOVETT ST | 6 | MILL & OVERLAY | AUGUST | 3 WEEKS |
LOVETT STREET | BRADFORD ST | FOSTER CT | 6 | MILL & OVERLAY | AUGUST | 3 WEEKS |
LOVETT STREET | FOSTER CT | BRADFORD ST | 6 | MILL & OVERLAY | AUGUST | 3 WEEKS |
FOSTER COURT | LOVETT ST | BALCOMB ST | 6 | MILL & OVERLAY | AUGUST | 3 WEEKS |
PIONEER TERRACE | LAFAYETTE PL | PIONEER TER | 5 | MILL & OVERLAY | SEPTEMBER | 5-6 WEEKS |
PIONEER TERRACE | LAFAYETTE PL | PIONEER TER | 5 | MILL & OVERLAY | SEPTEMBER | 5-6 WEEKS |
LAFAYETTE PLACE | SALEM ST | PIONEER TER | 5 | MILL & OVERLAY | SEPTEMBER | 5-6 WEEKS |
LAFAYETTE PLACE | PIONEER TER | GREEN ST | 5 | MILL & OVERLAY | SEPTEMBER | 5-6 WEEKS |
LAFAYETTE PLACE | GREEN ST | PIONEER TER | 5 | MILL & OVERLAY | SEPTEMBER | 5-6 WEEKS |
HOLLY STREET | LAFAYETTE ST | LINDEN ST | 5 | MILL & OVERLAY | SEPTEMBER | 3 WEEKS |
HOLLY STREET | LINDEN ST | HAZEL ST | 5 | MILL & OVERLAY | SEPTEMBER | 3 WEEKS |
AUBURN ROAD | MOFFATT RD | SURREY RD | 7 | MILL & OVERLAY | OCTOBER | 3 WEEKS |
SURREY RD | AUBURN RD | PICKMAN RD | 7 | MILL & OVERLAY | OCTOBER | 3 WEEKS |
PERSHING RD | SURREY RD | MOFFATT RD | 7 | MILL & OVERLAY | OCTOBER | 3 WEEKS |
PATTON RD | SURREY RD | DEAD END | 7 | MILL & OVERLAY | OCTOBER | 3 WEEKS |
MARION RD | BRADLEY RD | PRESTON RD | 7 | MILL & OVERLAY | OCTOBER | 3 WEEKS |
BORDER ST | CENTER ST | DEAD END | 4 | MILL & OVERLAY | OCTOBER | 3 WEEKS |
CENTER ST | SHILLABER ST | BORDER ST | 4 | MILL & OVERLAY | OCTOBER | 3 WEEKS |
SHILLABER ST | ORD ST | CENTER ST | 4 | MILL & OVERLAY | OCTOBER | 3 WEEKS |
ISLAND AVENUE | SUTTON AVE | DEAD END | 1 | MILL & OVERLAY | NOVEMBER | 3 WEEKS |
BAY VIEW AVENUE | FORT AVE | SUTTON AVE | 1 | MILL & OVERLAY | NOVEMBER | 3 WEEKS |
BAY VIEW AVENUE | SUTTON AVE | COLUMBUS AVE | 1 | MILL & OVERLAY | NOVEMBER | 3 WEEKS |
BEACH AVENUE | SUTTON AVE | COLUMBUS AVE | 1 | MILL & OVERLAY | NOVEMBER | 3 WEEKS |
COLUMBUS AVENUE | BEACH AVE | BAY VIEW AVE | 1 | MILL & OVERLAY | NOVEMBER | 3 WEEKS |
SUTTON AVENUE | BEACH AVE | ISLAND AVE | 1 | MILL & OVERLAY | NOVEMBER | 3 WEEKS |
SUTTON AVENUE | ISLAND AVE | BAY VIEW AVE | 1 | MILL & OVERLAY | NOVEMBER | 3 WEEKS |
TREMONT ST | MASON ST | GROVE ST | 6 | WHEELCHAIR RAMPS NEW SIDEWALK | COMPLETED | 4 WEEKS |
WILLSON ST | ACCESS RD | HIGH SCHOOL | 3 | WHEELCHAIR RAMPS SIDEWALK REPAIRS | AUGUST | 3 WEEKS |
ENGLISH ST | DERBY ST | ESSEX ST | 1 | SIDEWALK REPAIRS | SEPTEMBER | 4-5 WEEKS |
ALLEN ST | ENGLISH ST | WEBB ST | 1 | SIDEWALK REPAIRS | SEPTEMBER | 4-5 WEEKS |
COUSINS ST | ENGLISH ST | WEBB ST | 1 | SIDEWALK REPAIRS | SEPTEMBER | 4-5 WEEKS |
WEBB ST | DERBY ST | COUSINS ST | 1 | SIDEWALK REPAIRS | SEPTEMBER | 4-5 WEEKS |
FAIRMOUNT ST | LIBERTY HILL ST | NURSERY ST | 6 | SIDEWALK REPAIRS MILL & OVERLAY | OCTOBER/ NOVEMBER | 4 WEEKS PAVING TBD |
FAIRMOUNT ST | NURSERY ST | DEAD END | 6 | SIDEWALK REPAIRS MILL & OVERLAY | OCTOBER/ NOVEMBER | 4 WEEKS PAVING TBD |
*SCHEDULE SUBJECT TO CHANGE DUE TO WEATHER AND UNFORESEEN EXISTING CONDITIONS